Finished Project Chovdar Gold Mine, Azerbaijan

Chovdar Gold Mine, Azerbaijan

 

CONTRACT TYPE 

 Contractor to Aimroc
CONTRACTED AS Prime Contractor
CLIENT AIMROC (Azerbaijan International Mineral Resources Operating Company Ltd.)

STATUS Completed
COMPLETION November 2012

SERVICES PROVIDED

  •          Engineering & Design
  •          Procurement
  •          Manufacturing
  •          QA/QC Services
  •          ADR Plant Installation
  •          Turn-key Process and Exploration Laboratory
  •          Construction Management
  •          Commissioning and Start-up
  •          Staff Training

 

BACKGROUND

Chovdar site is located in the Khalnar Administrative District of the Azerbaijan Republic, approximately 45 km West of Ganja and 370 km North West of Baku. AIMROC is the largest mine company of Azerbaijan in association with Azerbaijan Government. We have built a gold processing plant with a capacity of 4 tons for AIMROC in Azerbaijan in 8 months’ time.

 

PROJECT DESCRIPTION

This project consist of 4 tons ADR plant with 5 Tanks of CIC system design, procurement, installation start–up and staff training, Pump station of heap leach design, procurement, installation,  Automation system, 2100 sample per month capacity process and exploration laboratory design, procurement, installation and staff training.