Finished Project Natalka Russia Gold Mine, Magadan,Russia

Natalka Russia Gold Mine, Magadan,Russia

 

PROJECT TYPE

Subcontractor to TOMC

STATUS Finished
CONTRACTED AS Subcontractor
CLIENT Polyus Equipment Provision
COMPLETION 2013
DESIGN PERIOD 245 days

SERVICES PROVIDED

  •          Structural Steel Design
  •          CIL Columns Design and Equipment Supply
  •          ADR Plant Design and  Equipment Supply
  •          Reagent Plant Design and Equipment Supply
  •          Automation System Design and Equipment Supply
  •          Quality Documentation
  •          Start-up, Commissioning and Operational Manuals

 

BACKGROUND

Located about 400 km away from the sea port of Magadan in the Far East of Russia, Natalka is one of the largest undeveloped gold deposits in the world. The mine is expected to have the processing capacity of 10 M tons of ore and approximately 500 thousand ounces of gold production annually at the launch of its operations. Following a stage by stage increase of the mill throughput to 40 M tons of ore annually, Natalka may potentially expand its production up to 1.5 M ounces of gold per year.

 

PROJECT DESCRIPTION

The project consist of 6 tone carbon capacity ADR plant Acid wash through to refinery, cascading CIL unit including 370 m³ each 10 tank and 8 reagent preparation units. We as CH Consultants have done basic and detail engineering as well as had procured the equipment.