Finished Project Vasgold Gold Mine - Kokshetau, Kazakhistan

Vasgold Gold Mine - Kokshetau, Kazakhistan

 

PROJECT TYPE  Subcontractor to Summit Valley
STATUS  Completed
CONTRACTED AS Subcontractor 
CLIENT Knelson Co. 
COMPLETION 2009 
DESIGN PERIOD 90 days 
CONSTRUCTION PERIOD 90 days 

SERVICES PROVIDED

  •          Structural Steel Manufacturing & Shipment
  •          Supervising of Piping, Structural Steel Installation, Equipment Installation
  •          Supplying of Pipes & Fittings
  •          Start-up & Commissioning

 

BACKGROUND

In Akmola region, approximately 15 kilometers from Kokshetau, there is unique gold deposit “Altyntau Kokshetau. Current productivity of the deposit is about 6 million tons of ore per year (8 million tons at full capacity). One ton of ore contains about 2 grams of gold. Thus, in future it will produce about 15 tons of gold a year. The project is one of the biggest gold mines of the world. CH engineering completed all structural steel manufacturing of ADR Plant in Turkey. Supervising Services for Erection of structural steel and equipment installation at the mine is provided.

Experienced team have overcome various problems and completed the project ahead of the schedule.

 

PROJECT DESCRIPTION

Vasgold Altyntau Kokshetau gold mine has CIL process and 6 tons of ADR Plant. We as CH Consultants, had completed 120 tons of structural steel manufacturing, erection, over 2000 meter of carbon steel and CPVC piping, All of ADR equipment installation and start – up