Finished Project Eti Gumus - Silver Mine, Kutahya, Turkey

Eti Gumus - Silver Mine, Kutahya, Turkey

 

PROJECT TYPE Prime Contractor
STATUS Completed
CONTRACTED AS Prime Contractor 
CLIENT Eti Gumus 
COMPLETION 2008 
DESIGN PERIOD 90 days 
CONSTRUCTION PERIOD 150 days 

SERVICES PROVIDED

  •          Supply and Installation of a Merril Crowe System
  •          Start-Up and Training of Merril Crowe System
  •          Fine Tuning of Merril Crowe System

 

BACKGROUND

Kutahya Etigumus silver mine is located in Gumuskoy province. The plant capacity is 12 M tons per year and total deposit of silver mine is100 M tons ore. One ton of ore contains about 10 - 180 grams of Silver. The project was very important to increase the silver recovery and to decrease the zinc consumption. Client was suffering from high chemical consumption and low production capacity. New plant designed and installed reduced the consumable quantity and increased Silver production greatly

 

PROJECT DESCRIPTION

As we CH Consultant, we designed and manufactured /importing a Merril-Crowe system (includes zinc feeder, pumps, filter press, de-aeration towers, pre coat tanks, fittings & pipes) due to specific conditions of the ore. Also we installed of the system, commissioning and training were included.