Finished Project Copler Gold Mine, Erzincan, Turkey

Copler Gold Mine, Erzincan, Turkey

 

PROJECT TYPE Prime Contractor
STATUS US Completed
CONTRACTED AS Prime Contractor 
CLIENT Cukurdere Mining 
COMPLETION 2008 
DESING PERIOD 90 days 
CONSTRUCTION PERIOD 150 days 

SERVICES PROVIDED

  •          Design and Manufacturing the CIL Columns of ADR Plant

 

BACKGROUND

Çöpler is located in the eastern part of Turkey, roughly 550 km east of Ankara and 120 km southwest of the city of Erzincan. The nearest population center is the town of ĺliҫ (population 2,500) which is 6km northeast of Çöpler. Çöpler’s attributable Proven and Probable Reserves totaled 74.4 Mt at an average grade of 1.4g/t gold for a total of 6 million contained ounces.  The project is one of the important new gold mining investments in Turkey. High quality manufactured steel tank with special rubber inner lining for the chemical and detox preparation system and the CIC tanks.

 

PROJECT DESCRIPTION

Çöpler Gold Mine has 4 tons of CIC and ADR plant, in this project scope; we completed design manufacture and transportation of CIC of ADR plant for increase CIC system capacity.