Finished Project Koza Gold - Mastra Gold Mine, Gumushane, Turkey

Koza Gold - Mastra Gold Mine, Gumushane, Turkey

 

PROJECT TYPE Prıme Contractor
STATUS Completed
CONTRACTED AS Supplier 
CLIENT Koza Gold A.S. 
COMPLETION 2009 
DESIGN PERIOD 90 days 
CONSTRUCTION PERIOD 150 days 

SERVICES PROVIDED

  •          Supplying and Installation of Electro-Winning Cells, Rectifiers, Sludge Pumps for ADR Plant

 

BACKGROUND

Mastra Gold Mine is situated at 22km of northwest of Gumushane and northeast of Mastra (Demirkaynak) village and south of East Pontyd Tecnotic band. Pontyd band is metallogenic zone well known with it’s completely spread massive sulphite deposits With the new technology electro-winning of the gold becomes more efficient and less costly due to lower chemical and power consumption

 

PROJECT DESCRIPTION

CH Supervision and installation teams completed manufacturing & installation of structural steel of electro – winning system, supply & installation of the electro- winning cell in ADR plant and start up all of electro-winning equipment and training of the staff.