Finished Project TÜPRAG (ELDORADO GOLD)/KIŞLADAĞ GOLD MINE II UŞAK, TURKEY

TÜPRAG (ELDORADO GOLD)/KIŞLADAĞ GOLD MINE II UŞAK, TURKEY

 

 CLIENT  Domestic Company
 STATUS  Completed
 CONTRACTED AS  Prime Contractor 
 DESIGN PERIOD  30 days 
CONSTRUCTION PERIOD

60 days

COMPLETION  2010 
   

SERVICES PROVIDED

  • Structural Steel Design & Manufacturing
  • CIC Columns Design & Manufacturing
  • Concrete Foundation Design & Construction
  • Start-Up & Commissioning
  • Staff Training

BACKGROUND

Kışladağ Gold Mine is located 30 km southwest of Uşak city in Turkey. The Kışladağ gold deposit is 180 M tons ore and one ton of ore contains about 1,07 grams of gold. Kışladağ Gold Mine is Europe’s biggest heap leach operation with 8 ton carbon process capacity. Existing CIC tanks had been corroded and needed to be replaced with shortest down time. CH Engineering planned all steps to be able keep production while installation. Project is completed 10 days ahead of strict schedule. Production capacity increased.

 

PROJECT DESCRIPTION

CH Site Team had completed 350 m2 concrete works, 100 ton of structure steel manufacturing and erection, manufacturing and installation of 10 each CIC tanks. Also CH site team had completed over 1500 meter of CS piping and all of the CIC train’s equipment start-up.