Ongoing Project Alamos Gold Mine, Kirazli, Turkey

Alamos Gold Mine, Kirazli, Turkey

 

PROJECT TYPE

EPCM

STATUS On going
CONTRACTED AS Prime Contractor 
CLIENT ALAMOS 
COMPLETION 2018
DESIGN PERIOD 114 days 
CONSTRUCTION PERIOD 60 days 

SERVICES PROVIDED 

  •          Detail engineering, procurement and construction management.

 

PROJECT DESCRIPTION

Alamos Kirazlı Gold mine is located in Canakkale Province on the Biga Peninsula of northwestern Turkey. Ağı Dağı is located about 50 kilometers southeast of Canakkale, and Kirazlı is located approximately 25 kilometers northwest of Ağı Dağı.

Alamos Kirazlı Gold Mine consists of heap leach area, CIC tank trains,4 tons ADR plants, all site infrastructure and superstructure system, 15000 Sample / month exploration and process control laboratory, crushing screening and conveying system  and site facilities. CH Consultants engineer team will have completed whole detailed engineering of mine system by the end of the project. With the completion of the project CH will also finalize the entire procurement and construction management services.